2002BD (MPW9H08)
Status
Complete
Application Date
03 June 2020
Allocation Decision Date
30 June 2020
Reservation Confirmation Date
03 July 2020
Design Submission Date
16 September 2020
Export Control Form Deadline
2020-09-16
Expected Delivery Date
09 April 2021
Actual Delivery Date
25 February 2021
Test Report Date
30 July 2021
Type
Shared
Broker
GF
Minimum Area
1mm2
Expected Number of Chips
50
Tentative
Click here to see your activities