1504MU
Status
Complete
Application Date
10 September 2015
Allocation Decision Date
31 July 2015
Reservation Confirmation Date
10 August 2015
Design Submission Date
30 September 2015
Expected Delivery Date
29 February 2016
Actual Delivery Date
17 December 2015
Test Report Date
31 March 2016
Type
On Demand
Broker
Minimum Area
Expected Number of Chips
0
Tentative