2204BF(MPW8X12)
Status
In Fab
Application Date
10 October 2022
Allocation Decision Date
31 October 2022
Reservation Confirmation Date
04 November 2022
Design Submission Date
07 December 2022
Export Control Form Deadline
2022-12-07
Expected Delivery Date
07 July 2023
Actual Delivery Date
24 May 2023
Test Report Date
31 October 2023
Type
Shared
Broker
GF
Minimum Area
1mm2
Expected Number of Chips
50
Tentative
Click here to see your activities