2502BD(MPW9H26)
Status
Complete
Application Date
10 June 2025
Allocation Decision Date
30 June 2025
Reservation Confirmation Date
04 July 2025
Design Submission Date
06 August 2025
Design Submission Date Upp
Export Control Form Deadline
2025-08-06
Export Control Date Upp
Expected Delivery Date
08 May 2026
Actual Delivery Date
20 April 2026
Test Report Date
31 August 2026
Type
Shared
Broker
GF
Minimum Area
1mm2
Expected Number of Chips
50
Tentative
Click here to see your activities