2507DA (MPW2274)


 
Status Accepting Design Data
Application Date 19 September 2025
Allocation Decision Date 31 August 2025   
Reservation Confirmation Date 05 September 2025
Design Submission Date 15 October 2025
Export Control Form Deadline 15 Oct (3 weeks ago)
Expected Delivery Date 17 April 2026
Test Report Date 31 July 2026
Type Shared
Broker GF
Minimum Area 1mm2
Expected Number of Chips 50
Tentative